A roots blower specification for electroplating and anodizing systems should define the process duty and site conditions clearly enough for suppliers to provide comparable quotations. A request based only on tank volume—such as “blower for a 20 m³ plating tank”—does not establish the required airflow, pressure, speed, motor power or discharge temperature.
Tank volume alone does not determine blower duty. Tanks with similar capacities can differ in liquid depth, solution density, sparger design, piping resistance and operating schedule. These factors affect the pressure the blower must overcome and the air each tank requires.
A complete request for quotation (RFQ) should state airflow at a defined reference condition, maximum differential pressure, operating cases, site environment, controls, air-quality requirements and package scope. This information helps suppliers assess whether a proposed blower can meet the stated conditions and gives the project team a consistent basis for technical and commercial comparison.
Describe the Process and Tank Duties
Begin with a concise description of every process supplied by the blower. Identify electroplating, anodizing, pickling, chemical cleaning, rinsing or another compatible application. State whether the air enters a liquid bath or serves a separate blow-off system. An air knife should be specified as its own duty because its flow and pressure requirements differ from submerged agitation.
For a centralized system, list each connected tank separately. The schedule should give the tank dimensions and normal and maximum liquid levels, solution density at relevant concentrations and temperatures, operating temperature, required airflow, sparger arrangement, branch length, production schedule and consequence of losing agitation. Include the process’s air-quality requirements, such as filtration needs or sensitivity to oil and particles.
Separate tank data helps identify which branches can share a header. A shallow rinse tank and a deep anodizing tank may require substantially different pressures. Grouping them on a common header without checking their individual requirements can lead to excess throttling on one branch or inadequate airflow on another.
The airflow case matrix should show which tanks operate together in minimum, normal, peak and planned future conditions. The peak demand is the sum of branches expected to run simultaneously; it is not automatically the total of every installed branch. Production staff should define realistic operating combinations. An unsupported assumption about simultaneous use can produce either an undersized system or an unnecessarily large blower.
For future expansion, identify the additional tanks, their expected airflow and pressure, their expected installation date and whether they will operate alongside existing equipment. The selected design allowance should cover identified uncertainty—such as measurement limitations or expected sparger deterioration—and be documented separately from planned future capacity. A general percentage added without a stated basis can shift the blower away from the required operating range.
Specify Airflow and Pressure on a Common Basis
Airflow and differential pressure are the two primary values used to evaluate a blower. Each flow value needs a reference basis. State whether it is actual volume at the blower inlet, actual volume at another measurement point, free-air flow, normal or standard volume, or a mass-flow equivalent. These quantities are not directly interchangeable.
For normal or standard volume flow, specify the reference temperature and absolute pressure. Different conventions can use different reference conditions. If the process calculation gives normal cubic metres per hour and the blower data gives actual inlet volume, convert the figures to a common basis before comparing them. Humidity may also be relevant, particularly where the inlet air is hot and humid.
State the required flow for each tank and the minimum, normal and maximum simultaneous system demand. Provide the most important operating combinations instead of one nominal value alone. Where tanks have different flow requirements, show them individually rather than assigning one average airflow to every branch.
The pressure requirement should represent the complete path from blower discharge to the point of air delivery. For tank agitation, the calculation typically includes liquid head, solution density, sparger resistance, branch and main-header losses, valves, fittings, instruments and package accessories. Use maximum credible liquid level and the relevant solution density for the demanding normal case.
Specify pressure as differential pressure across the blower, with inlet conditions stated. An outlet gauge reading alone may not define the duty. Use gauge and absolute pressure consistently; for most open-tank agitation systems, differential pressure is the relevant blower-selection value.
Separate the normal operating pressure from the maximum continuous pressure and any temporary abnormal pressure. State the relief-valve setting and automatic shutdown threshold independently, since these values serve different functions. A justified design allowance can account for known uncertainty or a defined change in system resistance, but excessive margin may increase motor size, energy use, discharge temperature, noise and purchase cost. It can also make protection settings and low-demand control more difficult.
The full operating schedule should show airflow and pressure for minimum, normal, peak and future cases, together with the duration of each case. This lets the supplier evaluate whether one variable-speed blower, multiple staged units or separate pressure groups fit the required range. The proposed machine must remain within its approved speed, pressure, power and temperature limits across all specified cases.
Include Site, Air-Quality and Control Requirements
Blower performance depends on inlet conditions. The RFQ should state site altitude, ambient and inlet temperatures, humidity where relevant, indoor or outdoor location, ventilation, dust and chemical mist exposure, nearby solvent vapour and available space. “Indoor installation” does not adequately describe a unit located beside open acid tanks.
Altitude changes atmospheric pressure and inlet-air density, while high ambient temperature can reduce air density and affect discharge temperature and cooling. Outdoor service also requires consideration of weather, drainage, frost, sunlight and wind-driven dust. These conditions should be considered with the intended operating schedule and the package’s cooling arrangement.
Even if the blower handles atmospheric air, the supplier should know what chemicals are present nearby and whether mist, vapour, washdown, splash or liquid backflow is credible. This information helps assess exposure of the base frame, enclosure, motor, panel, instruments, flexible connectors, fasteners and air piping. If corrosive or flammable gas will pass through the blower, state that explicitly; a standard air blower should not be assumed suitable for process-gas service.
Roots blowers do not normally inject lubricant into the compression chamber, but that does not guarantee air free of dust, moisture or chemical vapour. Specify particle limits, oil sensitivity, moisture limits, intake location, required filtration stages, pipeline cleanliness and any additional air treatment. If the application requires exceptionally clean air, define the measurable contamination criteria and where air quality will be assessed. Include pressure loss from filters, coolers or dryers in the system calculation, along with a suitable condensate-management arrangement where needed.
The control philosophy should be agreed before selecting the blower. State whether the system will use fixed speed, a variable-frequency drive (VFD), staged units, duty and standby machines, lead-lag rotation, pressure or flow control, tank demand signals or automatic branch isolation. For a VFD, specify minimum and maximum airflow, permitted speed range, control signal, start frequency and control ramp time. The blower must remain within the manufacturer-approved limits throughout the control range.
Describe restart behaviour after a power failure, emergency-stop requirements and any communication protocol. If the blower is permitted to run only while local exhaust ventilation is operating, include the required local-exhaust permissive and define the interlock response if exhaust is lost. A pressure-relief valve is a protective device; it should not be used as the normal means of regulating airflow.
Define Reliability, Electrical Supply and Package Scope
Reliability requirements depend on the consequences of losing agitation. State whether the installation needs one duty unit, a full-capacity standby, partial standby or a temporary emergency supply. If the standby machine is smaller than the duty unit, identify the critical tanks it must support. Specify whether transfer is manual or automatic and require an alarm when the primary unit fails.
The arrangement should permit an isolated blower to be serviced without reverse flow from another operating unit. Identify the required isolation and non-return valves and any shared-header constraints. These details affect both the package design and the site piping.
The electrical specification should include voltage, phase, frequency and tolerance; motor efficiency and enclosure; insulation and temperature-rise requirements; hazardous-area classification where applicable; and VFD compatibility. State the motor starting method, such as direct-on-line, soft starter or VFD, based on the site electrical system and the project’s starting requirements.
If the customer supplies the motor, the blower supplier should provide required shaft power, rotational speed and drive information for each operating case. The final motor rating should cover the greatest approved absorbed power at the specified conditions with an agreed margin. Nominal motor power is not the same as electrical input at the operating point.
For a belt-driven package, give the required speed and any restrictions on adjustment. Changing the pulley or drive ratio changes blower speed and can affect airflow, power, temperature, noise and mechanical loading. A pulley change should not be treated as a routine capacity adjustment unless the resulting speed remains within the approved limits.
List the package components and services expected in the offer. These may include the blower and motor, base and drive, guards, inlet filter, silencers, relief and non-return valves, flexible connectors, instruments, vibration protection, enclosure, controls, foundation items, lubricant, tools, commissioning and spare parts. State who provides interconnecting piping, isolation valves, branch-flow instruments and spargers. Agreeing the package boundary during the enquiry reduces the risk of missing equipment and installation delays.
Set Measurable Performance and Acceptance Criteria
Noise requirements should be objective and measurable. Define the sound-pressure limit, measurement positions and distance, operating condition, number of units running and whether an acoustic enclosure is installed. State the noise weighting used for the reported sound level and how background noise correction will be handled. Keep package measurements distinct from sound levels in the finished room, where reflections, pipe resonance, tank bubbling and nearby machinery can affect results.
Request performance data for the specified cases. The offer should identify the model and speed, delivered flow at the stated reference condition, differential pressure, shaft power, motor rating, discharge temperature, sound data, permitted pressure and speed range, connections, dimensions and mass. Ask the supplier to identify whether each quoted value is guaranteed, calculated, typical or subject to tolerance. Each guaranteed performance value should be tied to the relevant inlet conditions and test basis.
A maximum catalogue airflow at little or no pressure does not establish capacity at the required differential pressure. Confirm that the proposed points fall within the manufacturer’s approved performance range and that motor load and discharge temperature are acceptable at the most demanding specified case.
Quotations should be compared on the same technical basis. Review airflow reference conditions, actual duty pressure, blower speed, absorbed power, motor rating, discharge temperature, accessories, noise measurement conditions, control range, operating limits, standby arrangement, documentation and service. A smaller motor rating alone does not prove better efficiency, and a larger blower is not automatically safer. Compare actual duty data and included scope, not isolated headline values.
Agree the required drawings and records before manufacturing begins. The document list may include arrangement and foundation drawings, connection dimensions, performance curves, motor and instrument data, valve information, electrical and control documents, installation and maintenance manuals, lubricant and spare-parts information, inspection records, and material or coating details. State the required language, format and number of copies.
Acceptance criteria should distinguish package performance from the installed system’s performance. Inspection may cover visual and dimensional checks, mechanical running, vibration and noise, applicable pressure or leak checks, motor and instrument verification, and review of certificates. If the project requires a witnessed factory test, specify the procedure, instruments, test conditions, acceptance limits, witness arrangements and required records in the RFQ.
A factory test cannot reproduce every site condition. Installed airflow and pressure also depend on customer piping, spargers, valves, intake environment and operating lineup. Site acceptance should therefore identify which results apply to the blower package and which apply to the complete agitation system, with the measurement points and operating cases agreed in advance.
Glossary
Airflow case matrix: Schedule showing the tanks expected to operate together and the airflow and pressure required in each scenario. It helps define credible minimum, normal and peak system demands.
Background noise correction: Adjustment used when ambient sound contributes to a measured equipment sound level. The measurement procedure should state how background sound is assessed and treated.
Control ramp time: Period over which a controller changes blower speed or output after receiving a command. It influences how quickly the system responds to changing demand.
Design allowance: Documented margin added to a calculated requirement for a specific uncertainty or expected change in conditions. It should have a stated basis and should not replace analysis of the actual duty.
Drive ratio: Relationship between motor speed and blower speed established by the transmission components. Changing it alters blower speed and can affect performance and mechanical limits.
Guaranteed performance value: A value the supplier contractually commits to meet under defined operating and test conditions. The offer should distinguish it from calculated or typical data.
Local-exhaust permissive: Control condition that allows a process-related device to operate only when the designated exhaust system is available. The interlock response to loss of exhaust should be defined in the project control logic.
Motor starting method: Electrical arrangement used to accelerate the motor from rest, such as direct-on-line starting, a soft starter or a VFD. Selection depends on the motor, blower drive and site electrical requirements.
Noise weighting: Frequency adjustment applied when reporting a sound measurement, such as A-weighting. Sound levels should be compared only when the weighting and measurement conditions are stated consistently.
Witnessed factory test: Factory test attended by the customer or its representative under an agreed procedure. The test plan should identify the measured parameters, acceptance criteria and records to be provided.